| Extent of the works: Demolition
of a school building in the municipality of Caluso
(TO) which had become unstable as a result of ground
movement.
The delicate nature of the operation was due to the location
of the building, which was in the historic centre
adjacent to shops and homes.
The demolition of the buildings in their urban setting involved
the use of technologically innovative plant and equipment,
in order to guarantee minimum environmental impact in terms
of minimum noise and dust levels. The result was fewer repercussions
in terms of public wellbeing, with reduced vibration and noise
propagation.
Tutto ciò consente minori ripercussioni a tutela dei
cittadini, limitando vibrazioni e propagazione dei rumori.
The demolition involved a total volume of 40.000 cubic
metres up to heights of approximately 15 metres.
| Caluso |
| WORKS
DURATION |
2 months |
| PLANT |
21 ton excavators
equipped with a 30 m boom, hydraulic grippers and crusher
17.5 ton excavators equipped with hydraulic crusher and
breaker hammer
10 ton excavators equipped with sorting grabber
mobile crushing plant |
| Volume |
Approximately 40,000
cubic metres |
|